The installation of the 600 box-girders: a chapter that has come to an end
Published on 10 October 2018
An important chapter in the history of the new Champlain Bridge construction is completed with the end of the box-girders installation of its approaches. Indeed, the conclusion of this work is also the end of an exciting adventure:
- Design of these parts in 2015
- Fabrication at CANAM and its subcontractors from February 2016 to June 2018
- Delivery on site from November 2016 to September 2018
- Installation at the West Approach : August 2017 to early October 2018
- Installation at the East Approach : January 2018 to September 2018
There are several teams to congratulate for this enormous achievement: engineers, welders, carriers, ironworkers, crane operators, maneuvers, boat captains and sailors, and many others. This progress shows without any doubts that the completion of the new Champlain Bridge is underway.